Upgrades to Tanbark Road
This project is closed.
The Town of Niagara-on-the-Lake worked with R.V. Anderson Associates Limited, an engineering consultant, to develop a permanent solution for the drainage issues on Tanbark Road.
The work consisted of the following:
- Installation of approximately 650m of 300mm diameter PVC Watermain;
- Installation of approximately 400m of 375mm diameter Storm Sewer; and,
- Approximately 700m of road reconstruction included asphalt, sidewalks, curb, and gutter.
This project was identified as high-priority and the Town has taken into consideration all of the feedback provided by the residents of the area.
This project is closed.
The Town of Niagara-on-the-Lake worked with R.V. Anderson Associates Limited, an engineering consultant, to develop a permanent solution for the drainage issues on Tanbark Road.
The work consisted of the following:
- Installation of approximately 650m of 300mm diameter PVC Watermain;
- Installation of approximately 400m of 375mm diameter Storm Sewer; and,
- Approximately 700m of road reconstruction included asphalt, sidewalks, curb, and gutter.
This project was identified as high-priority and the Town has taken into consideration all of the feedback provided by the residents of the area.
-
Tanbark Road Construction Start Date
Share Tanbark Road Construction Start Date on Facebook Share Tanbark Road Construction Start Date on Twitter Share Tanbark Road Construction Start Date on Linkedin Email Tanbark Road Construction Start Date linkThe Tanbark Road Storm Sewer, Watermain and Road Reconstruction has been awarded to Peters Construction Group Ltd. and is set to begin the week of July 9, 2018. The project is scheduled for approximately 15 weeks, weather permitting.
At times there may be some inconvenience to you during the construction period and we respectfully request your patience and co-operation during this period. Should access to your driveway be interrupted, you will be given notice from the contractor. Access to driveways will be restored daily. Work hours will typically be 7:00 a.m. to 5:00 p.m., Monday to Friday.
The Tanbark Road Storm Sewer, Watermain and Road Reconstruction has been awarded to Peters Construction Group Ltd. and is set to begin the week of July 9, 2018. The project is scheduled for approximately 15 weeks, weather permitting.
At times there may be some inconvenience to you during the construction period and we respectfully request your patience and co-operation during this period. Should access to your driveway be interrupted, you will be given notice from the contractor. Access to driveways will be restored daily. Work hours will typically be 7:00 a.m. to 5:00 p.m., Monday to Friday.
-
Open House Update
Share Open House Update on Facebook Share Open House Update on Twitter Share Open House Update on Linkedin Email Open House Update linkTown Engineering staff will be holding an open house for the Tanbark Road Storm Sewer, Watermain and Road Reconstruction Project on February 12, 2018 from 4:00 pm to 7:00 pm. Residents of the affected area are encouraged to come to the Operations building located at 3 Lorraine Street, Niagara-on-the-Lake (behind Town Hall) to review the parameters of the project. Local residents along Tanbark Road will be notified by written notice during the week of February 5, 2018.
Town Engineering staff will be holding an open house for the Tanbark Road Storm Sewer, Watermain and Road Reconstruction Project on February 12, 2018 from 4:00 pm to 7:00 pm. Residents of the affected area are encouraged to come to the Operations building located at 3 Lorraine Street, Niagara-on-the-Lake (behind Town Hall) to review the parameters of the project. Local residents along Tanbark Road will be notified by written notice during the week of February 5, 2018.
-
Open House and Tendering Process
Share Open House and Tendering Process on Facebook Share Open House and Tendering Process on Twitter Share Open House and Tendering Process on Linkedin Email Open House and Tendering Process linkThe Town of Niagara-on-the-Lake and R.V. Anderson Associates Ltd. are near completion of the detailed design for this project and will be holding an open house in February 2018 to allow local residents to comment on the design for the Tanbark Road Watermain, Storm Sewer and Road Reconstruction project.
The project will be open for a public tendering period from April 2, 2018, to April 17, 2018. A recommendation for the award of the project to the lowest bidder will be brought to Council for approval on May 14, 2018. The targeted start of construction will be early-to-mid June 2018Continue reading
The Town of Niagara-on-the-Lake and R.V. Anderson Associates Ltd. are near completion of the detailed design for this project and will be holding an open house in February 2018 to allow local residents to comment on the design for the Tanbark Road Watermain, Storm Sewer and Road Reconstruction project.
The project will be open for a public tendering period from April 2, 2018, to April 17, 2018. A recommendation for the award of the project to the lowest bidder will be brought to Council for approval on May 14, 2018. The targeted start of construction will be early-to-mid June 2018, subject to the Town receiving all required Ministry approvals.
Photos
Who's Listening
Life Cycle
-
Detailed Design
Upgrades to Tanbark Road has finished this stageThe Town of Niagara-on-the-Lake and R.V. Anderson Associates have completed the detailed design for the installation of the watermain, storm sewers and road reconstruction improvements.
-
Local Resident Feedback
Upgrades to Tanbark Road has finished this stageThe Town will be holding an open house early February to discuss some of the key features of this project. At that time, residents will be invited to express any issues or concerns related to this project.
-
Tendering Process
Upgrades to Tanbark Road has finished this stageThe tender selection process will begin in mid April and will be open to all contractors, pending final approval from Council.
-
Construction Start Date
Upgrades to Tanbark Road is currently at this stageThe construction start date is set for the week of July 9, 2018.