Upgrades to Tanbark Road
Share on Facebook
Share on Twitter
Share on Linkedin
Email this link
The Town of Niagara-on-the-Lake is currently working with R.V. Anderson Associates Limited, an engineering consultant, to develop a permanent solution for the drainage issues on Tanbark Road.
The work will consist of the following:
- Installation of approximately 650m of 300mm diameter PVC Watermain;
- Installation of approximately 400m of 375mm diameter Storm Sewer; and,
- Approximately 700m of Road Reconstruction including asphalt, sidewalks, curb, and gutter.
This project has been identified as high-priority and the Town has taken into consideration all of the feedback provided by the residents of the area. The intent is to implement a permanent solution as soon as possible.