Upgrades to Tanbark Road

Share on Facebook Share on Twitter Share on Linkedin Email this link
Tanbark Road Construction

The Town of Niagara-on-the-Lake is currently working with R.V. Anderson Associates Limited, an engineering consultant, to develop a permanent solution for the drainage issues on Tanbark Road.

The work will consist of the following:

  • Installation of approximately 650m of 300mm diameter PVC Watermain;
  • Installation of approximately 400m of 375mm diameter Storm Sewer; and,
  • Approximately 700m of Road Reconstruction including asphalt, sidewalks, curb, and gutter.

This project has been identified as high-priority and the Town has taken into consideration all of the feedback provided by the residents of the area. The intent is to implement a permanent solution as soon as possible.


The Town of Niagara-on-the-Lake is currently working with R.V. Anderson Associates Limited, an engineering consultant, to develop a permanent solution for the drainage issues on Tanbark Road.

The work will consist of the following:

  • Installation of approximately 650m of 300mm diameter PVC Watermain;
  • Installation of approximately 400m of 375mm diameter Storm Sewer; and,
  • Approximately 700m of Road Reconstruction including asphalt, sidewalks, curb, and gutter.

This project has been identified as high-priority and the Town has taken into consideration all of the feedback provided by the residents of the area. The intent is to implement a permanent solution as soon as possible.


  • Tanbark Road Construction Start Date

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The Tanbark Road Storm Sewer, Watermain and Road Reconstruction has been awarded to Peters Construction Group Ltd. and is set to begin the week of July 9, 2018. The project is scheduled for approximately 15 weeks, weather permitting.

    At times there may be some inconvenience to you during the construction period and we respectfully request your patience and co-operation during this period. Should access to your driveway be interrupted, you will be given notice from the contractor. Access to driveways will be restored daily. Work hours will typically be 7:00 a.m. to 5:00 p.m., Monday to Friday.

  • Open House Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Town Engineering staff will be holding an open house for the Tanbark Road Storm Sewer, Watermain and Road Reconstruction Project on February 12, 2018 from 4:00 pm to 7:00 pm. Residents of the affected area are encouraged to come to the Operations building located at 3 Lorraine Street, Niagara-on-the-Lake (behind Town Hall) to review the parameters of the project. Local residents along Tanbark Road will be notified by written notice during the week of February 5, 2018.

  • Open House and Tendering Process

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The Town of Niagara-on-the-Lake and R.V. Anderson Associates Ltd. are near completion of the detailed design for this project and will be holding an open house in February 2018 to allow local residents to comment on the design for the Tanbark Road Watermain, Storm Sewer and Road Reconstruction project.

    The project will be open for a public tendering period from April 2, 2018, to April 17, 2018. A recommendation for the award of the project to the lowest bidder will be brought to Council for approval on May 14, 2018. The targeted start of construction will be early-to-mid June 2018, subject to the Town receiving all required Ministry approvals.


Page last updated: 09 Jul 2018, 02:51 PM