Share Cannery Park on FacebookShare Cannery Park on TwitterShare Cannery Park on LinkedinEmail Cannery Park link
The Town of Niagara-on-the-Lake would like to thank everyone who came out to all the public meetings. The feedback on the Master Plan was great.
We have added a FAQ section for this park. Also, we have selected the playground supplier and have scheduled an Open house (see Key Dates)
We want to hear from you! There are two ways you can participate. First, click the “Survey & Forms” tab and vote on where you think the Community Information Board should be located and playground colours. Second, click the “Feedback” tab and tell us your opinion about the playground designs. Public engagement will be taken on this Join the Conversation page until August 30, 2019.
Town staff talked with our Playground contractor and we can make some modifications to the existing playground plan. We need your input for the elements you would like to see. Please keep in mind that the budget and the space for the playground will not change.
The Town of Niagara-on-the-Lake would like to thank everyone who came out to all the public meetings. The feedback on the Master Plan was great.
We have added a FAQ section for this park. Also, we have selected the playground supplier and have scheduled an Open house (see Key Dates)
We want to hear from you! There are two ways you can participate. First, click the “Survey & Forms” tab and vote on where you think the Community Information Board should be located and playground colours. Second, click the “Feedback” tab and tell us your opinion about the playground designs. Public engagement will be taken on this Join the Conversation page until August 30, 2019.
Town staff talked with our Playground contractor and we can make some modifications to the existing playground plan. We need your input for the elements you would like to see. Please keep in mind that the budget and the space for the playground will not change.
Share Do you like the New playground equipment? on FacebookShare Do you like the New playground equipment? on TwitterShare Do you like the New playground equipment? on LinkedinEmail Do you like the New playground equipment? link
McWilliams and Associates is working with the Town to detail the tender specifications
Park Design - Tender
Cannery Park has finished this stage
Park construction is out for tender
Public Open House - Playground Design
Cannery Park has finished this stage
Playground contractor selected. Playground design presented to the general public for feedback. Open house scheduled for August 19, see Key Dates for more information. Deadline for feedback is August 30
New Playground Designs
Cannery Park has finished this stage
The Town has reviewed the comments from JTC and have worked with contractor on a redesign. Please let us know your feedback. Deadline for feedback will be Sept 24.
Construction of the Playground
Cannery Park is currently at this stage
Construction will begin November 11 with the excavations and installation of curbing. Installation of the equipment is scheduled for November 18.
Re-Tender of the Site Works
this is an upcoming stage for Cannery Park
Tender packages will be sent out in the Winter of 2020.
Contractor Selection
this is an upcoming stage for Cannery Park
Tender packages are reviewed by Town staff. A contractor is selected and a construction schedule is set.
Park Under Construction
this is an upcoming stage for Cannery Park
The successful contractor is executing the design.